Current utility projects
Updated April 2012
This page is updated monthly.
Waste management services
780-449-5514
No current projects
Water & wastewater services
780-467-7785 - 24-hour numberDistribution & Collection system
Darrin Wenzel 780-467-7785
- Catch basin cleaning at various locations in Sherwood Park scheduled start up in May 2012
- Main line valve turning at various locations in Sherwood Park scheduled start up in April 2012
- Main line cleaning at various locations in Sherwood Park
- Mills Haven area
- Glen Allen
- Hydrant repair / replacement
- H-5420 8430 24 St
- Wastewater repair / replacement
- 2110 91 Ave
- 2404 91 Ave
- Mission St
- Storm line repair / replacement
- Greystone Court
- Sandpiper Drive
- Fir Street
Service lateral rehabilitation
Sump pump retrofit program
- Catalina Dr
- Coachman Manor
- Hillside Cr
- Calico Dr
- Cheyenne Cr
- Darlington Pl
- Craigavon Est
- Highland Way
- Highland Cr
Utilities engineering
780-467-7785
Improvements to the Strathcona County Water Supply System (SCWSS)
- 34th Street booster station - October 3, 2011 - July 31, 2012
- Water transmission main between 17th Street reservoir and Lakeland Drive
- 17 Street Reservoir Expansion
The purpose of the SCWSS is to ensure Strathcona County residences continue to receive adequate water supply and pressure and to meet ultimate water demand conditions when Sherwood Park is built out to it's boundaries.
34th Street booster station - October 3, 2011 - July 31, 2012
Dusyn Hehr 780-467-7785
Upgrading the existing booster station to meet the requirements at the new 17th street reservior. The project consists of a new addition to the existing building as well as two new pumps.
Water transmission main between 17th Street reservoir and Lakeland Drive
Shawn Olson 780-467-7785

Strathcona County is installing a waterline in the Transportation Utility Corridor (TUC) that runs parallel to Highway 216, east of the highway between 92 Avenue and Petroleum Way. The work is scheduled to be complete in the summer of 2012.
17 Street Reservoir Expansion
Shawn Olson 780-467-7785
Construction of the 17th Street Reservoir and Pumphouse Expansion is almost complete! As part of the Strathcona County's Water Supply System (SCWSS), a portion of phase one ($20 million project) commenced May 2009 and is estimated to be completed in the spring of 2012.
More information and photosNorthern Bear water line October 11, 2011 - Spring 2012
Dustyn Hehr 780-467-7785
This water line is being installed by directional drill method. It will be connected to the Northern Bear reservior.
Half Moon Lake fill station October 2, 2011 - February 2012
Dustyn Hehr 780-467-7785
Construction of a truck fill station for Strathcona County residents will begin this year and open to the public early 2012.