New weight restriction on Main Street bridge

The weight restriction on Pointe-Aux-Pins Creek bridge on Main Street in Ardrossan has been decreased to 10 tonnes (10,000 kg). See map.

Please use alternate routes. 

The new weight restriction protects the stability of the bridge and the safety of all motorists.  

Complete bridge replacement is planned for 2025, pending regulatory approvals.   

Last modified: Feb. 13, 2024, 3:47 p.m.

The Ardrossan Hamlet Roads Upgrade project will enhance road safety, efficiency and usability for residents.

The planning, design and construction of this multi-phased project is scheduled to take place from fall 2015 into the coming years, pending Council approval of annual budgets.

View a map of the concept. (3.1 MB)

 


Pointe-Aux-Pins Creek Bridge

With the Main Street loop completed, and further development happening in the Hamlet of Ardrossan, the bridge crossing Pointe-Aux-Pins Creek needs to be replaced. The narrow bridge is not built to accommodate the increased demands. The scope of this project component consists of upgrading the current Pointe-Aux-Pins Creek Bridge into a 9.0m two-lane, rural, standard collector road with a 3.0m asphalt trail located on the west side of the new bridge.

Project timeline

This project is currently in the Design phase.

Project Timeline - Design

  • March 2020 – Final bridge design was delivered by the consultant. This project is currently scheduled for construction in 2025, pending regulatory approvals.
  • March 2018 – Design completed.
  • August 2017 – Consultant selected to complete preliminary and detailed design.

Main Street

The scope of this project component is to upgrade Main Street from Range Road 221A to Arbour Close into a two-lane, standard rural collector road. The project will include the construction of approximately 250 meters of sidewalk on the west side of the road. In addition, some minor traffic calming will be introduced at the intersection of Third and First Avenue.

Project timeline

This project is currently in the design phase and scheduled for construction in 2025, pending funding and regulatory approvals.

Project Timeline - Design

Timeline still to be determined.


Range Road 221A

The scope of this project component is to upgrade Range Road 221A from Queen Street to King Street into a two lane, rural, standard collector road. The project will include constructing approximately 325 meters of roadway upgrades.

Project timeline

This project is at the design phase. This project is currently not included in the 2022 - 2026 budget plan.

Project Timeline - Design


Queen Avenue and Third Street

This project is now substantially complete. A small amount of maintenance is scheduled during the next two years and a final acceptance inspection is scheduled in the fall of 2019.

Third Avenue was upgraded into a two lane, rural, standard collector road with a sidewalk on the south side of the road. Queen Street was upgraded into a two lane rural and urban standard collector road, with sections of sidewalk on both sides of the road.

Project timeline

This project is currently completed.

Project complete

  • September 2017: a substantial completion inspection was conducted.
  • August 29, 2016: construction work began on Third Avenue.
  • An Open House was held on November 25, 2015.

Additional background


Further information:

Transportation Engineering and Operations
Phone: 780-417-7100
Submit a question about this project